STEP-BY-STEP GUIDE WITH CHECKLIST
How to organise an event: from first idea to final sign-off
There is no single event permit in the UK. Permission is assembled from separate consents held by different bodies: the landowner, the licensing authority, the highway authority and, in two-tier areas, those last two sit in different councils. Each has its own clock, and the slowest one sets your timeline.
Below is the full sequence in 9 steps, with a tick-box checklist for every stage. The emphasis is on the part where organisers actually get stuck, the documents a council expects to see attached. We know that side well: 90+ municipalities assess incoming site plans and traffic plans inside our software, so we see exactly what gets sent back.
01 THE SEQUENCE
Why UK event permission is a stack, not one permit
Most event-planning guides start with the concept and the budget. That is correct, but it hides the real constraint, which is that four separate bodies each have to say yes and none of them talks to the others by default. The landowner controls the ground. The licensing authority handles alcohol, regulated entertainment and late-night refreshment under the Licensing Act 2003. The highway authority controls any closure, diversion or sign on the public road. Environmental health, the fire service and the police each carry their own statutory powers over noise, safety and public order.
The council's Safety Advisory Group is where those strands get pulled together, and it is the part organisers most often misread. A SAG is non-statutory. It has no power to approve an event and no power to ban one, and it does not take on any of your responsibilities as organiser. What it does is put every agency in the same room, which means an unanswered comment in a SAG meeting tends to reappear later as a formal objection from a body that can act on it.
Because the clocks run in parallel and none of them is short, work backwards from the longest one instead of forwards from today. A temporary traffic regulation order for a road closure typically needs a minimum of 12 weeks with most highway authorities, since the order has to be advertised and consulted on. A premises licence carries a 28 day consultation. Councils commonly want event notification 6 weeks ahead below 500 people and 6 months or more above 1,000. If your event is 4 months away, the drawings are not a spring project, they are a next-fortnight project.
02 THE STEPS
How to organise an event in 9 steps
The timeline below assumes a medium-sized outdoor public event on or beside a public road in England or Wales. For a private indoor event you can run the highways and licensing steps much lighter. For anything above 5,000 people, add several months to the front.
12 to 9 months ahead
Fix the concept, the capacity figure and the budget
Write down what the event is for, who it is for, and how many people you expect on site at peak. That capacity figure is the single input that drives everything after it: whether a temporary event notice is enough, how much notice your council wants, how many stewards and toilets you need, and which tier of duty applies once Martyn's Law commences. Build the budget around that number and hold 10 to 15 per cent back for contingency.
12 to 6 months ahead
Secure the land in writing before anything else
Permission to use the ground is separate from every licence and order that follows. Council parks, market squares and closed streets are booked through the parks or events team, usually with a hire agreement, a damage bond and proof of insurance. Private land needs the owner's written consent. Nothing else on this list is worth starting until the site is confirmed, because the whole permission stack is site specific.
9 to 6 months ahead
Notify the council and get onto the SAG agenda
Most councils run an event notification form that feeds their Safety Advisory Group. Notice periods differ by council: many ask around 6 weeks for events under 500 people, about 3 months for 500 to 1,000, 6 months above that, and 9 months for anything over 5,000. Send the form early even if the plan is half formed. A SAG is non-statutory and cannot approve or prohibit your event, but the police, fire service and environmental health officers around the table do hold statutory powers, and the legal duty for public safety stays with you either way.
6 to 4 months ahead
Choose the licensing route: TEN or premises licence
If you are selling alcohol, putting on regulated entertainment, or serving hot food or drink between 11pm and 5am, you need cover under the Licensing Act 2003. Below 500 people at any one time and up to 7 days, a temporary event notice usually does the job. Above that, or for a site you will use again and again, you need a premises licence, which runs a 28 day consultation and requires a scale plan of the premises. Scotland uses occasional licences from the licensing board instead, and Northern Ireland has its own regime, so confirm the route with the licensing team before you build the bar.
6 to 3 months ahead
Apply for road closures and traffic management
Closing a road is a separate application to the highway authority, which in two-tier areas is the county council rather than the district that handles your licence. Most highway authorities need at least 12 weeks for a temporary traffic regulation order, because it has to be advertised and consulted on, and a closure for a large annual event can take considerably longer. Street parties and small community closures often run through a shorter order, but still count in weeks, not days.
4 to 2 months ahead
Write the event management plan
The event management plan is the document the SAG reads. Most councils publish their own template and the sections repeat: overview and capacity, site plan, crowd management, stewarding and SIA-licensed security, traffic and parking, medical cover, fire safety and evacuation, noise, waste and welfare, communications and the incident procedure. Risk assessments and drawings go in as annexes. Version the file clearly so every agency is commenting on the same draft.
3 to 1 month ahead
Contract suppliers, traders and crew
Book the long lead items first: stages, marquees, toilets, fencing, power, security and traffic management. Collect each supplier's paperwork as you go, because the council will ask for it: insurance, method statements, structural calculations for stages and temporary demountable structures, gas and electrical certificates. Food traders must be registered with a local authority, and registration takes 28 days, so chase that now instead of in event week.
Final 4 weeks
Finalise the plans, brief the team, tell the neighbours
Send the final version of the event management plan to the SAG at least a week before the event rather than on the day. Publish the closure and diversion details to residents, businesses and bus operators, and put the same information where ticket holders will see it. Run a briefing for stewards and supervisors covering the site plan, the evacuation routes, the radio channels and who has the authority to stop the show.
Event week and afterwards
Build, walk the site, then debrief and archive
Walk the built site against the approved plan with your safety officer, and with the licensing or environmental health officer where the council asks for it. Check that fire lanes are the width you drew, that no exit has ended up behind a bar, and that every sign on the diversion route is in place and facing the right way. Afterwards, take the signs down, hand the site back in the agreed condition, and hold the debrief while everyone still remembers the detail.
03 THE CHECKLIST
Event planning checklist
The same 9 stages, now as a tick list. Work through it stage by stage and keep it open beside your event management plan.
1. Fix the concept, the capacity figure and the budget
12 to 9 months ahead
- Purpose, audience and peak capacity written down
- Date checked against the local events calendar and school holidays
- Budget set with 10 to 15 per cent contingency
- Legal entity, bank account and liability position settled
2. Secure the land in writing before anything else
12 to 6 months ahead
- Site confirmed in writing for build days, event days and break days
- Hire agreement, bond and reinstatement terms read line by line
- Public liability insurance arranged (councils commonly set £5 million)
- Access gates, load-in points, power and water checked on site
3. Notify the council and get onto the SAG agenda
9 to 6 months ahead
- Event notification form submitted to the council
- SAG meeting dates and document deadlines in the diary
- Named contacts at licensing, highways and environmental health
- Asked which documents this council wants, and in which format
4. Choose the licensing route: TEN or premises licence
6 to 4 months ahead
- Licensable activities listed and matched to the right route
- TEN given at least 10 clear working days ahead, or
- Premises licence lodged with room for the 28 day consultation
- Personal licence holder or designated premises supervisor named
- Age verification, drinks and refusals policy written down
5. Apply for road closures and traffic management
6 to 3 months ahead
- Road closure application lodged with the highway authority
- Signed diversion route agreed, including buses and HGVs
- Accredited traffic management contractor booked
- Emergency vehicle access kept clear and marked on the plan
- Residents, businesses and bus operators notified
6. Write the event management plan
4 to 2 months ahead
- Event management plan drafted on the council's own template
- General and fire risk assessments attached
- Medical cover scaled to capacity and audience profile
- Steward numbers, briefing plan and SIA cover confirmed
- Site plan, traffic plan and signage plan attached as annexes
7. Contract suppliers, traders and crew
3 to 1 month ahead
- Stages, marquees, toilets, fencing and power contracted
- Security, stewards and traffic management contracted
- Supplier insurance, method statements and structural certificates collected
- Food traders registered and hygiene ratings checked
- Build and break times agreed in writing with every supplier
8. Finalise the plans, brief the team, tell the neighbours
Final 4 weeks
- Final event management plan issued at least 7 days ahead
- Residents, businesses and bus operators notified in writing
- Steward and supervisor briefing pack issued
- Radio channels, call signs and escalation chain agreed
- Contact sheet with 24 hour numbers circulated
9. Build, walk the site, then debrief and archive
Event week and afterwards
- Site walked against the approved site plan before doors open
- Fire lanes, exits and emergency access clear and measured
- Every diversion and event direction sign checked in position
- Signs, barriers and infrastructure removed, site handed back
- Debrief held and all drawings archived for the next edition
04 LICENSING
Temporary event notice: when a TEN covers you, and when it does not
A temporary event notice is the light-touch route under the Licensing Act 2003 in England and Wales. It covers licensable activities at a site that is not already licensed for them: selling alcohol, providing regulated entertainment such as live or recorded music, and serving hot food or drink between 11pm and 5am. You give the notice to the council, and you copy it to the police and to environmental health.
The limits are strict and they are where events come unstuck. Fewer than 500 people on site at any one time, crew and traders included. No longer than 168 hours, which is 7 days. The fee is £21. A single premises can carry up to 15 notices a year up to a combined 21 days, and an individual can give 5 a year, rising to 50 if they hold a personal licence.
Timing matters more than the form. A standard TEN needs at least 10 clear working days before the event, and clear means the day it arrives, the day of the event, weekends and bank holidays all drop out of the count. A late TEN, given 5 to 9 working days ahead, is possible but fragile: if the police or environmental health object to a late notice, it is simply invalid and the activity cannot go ahead, with no hearing to argue your case.
Push past 499 people, run longer than a week, or use the same field every month and you are into premises licence territory instead. That application runs a 28 day consultation during which responsible authorities and members of the public can make representations, and it must be accompanied by a scale plan of the premises, normally drawn at 1:100 unless the licensing team agrees otherwise in writing. Scotland has no TEN at all: unlicensed premises apply to the licensing board for an occasional licence, capped at 14 days, and boards in practice want the application around 28 days out. Northern Ireland runs a different system again.
05 THE MAIN DOCUMENT
Event management plan: what the council actually asks for
There is no statutory template for an event management plan. Each council publishes its own, so download the one your council uses rather than a generic version, but the contents are consistent enough to prepare in advance: event overview and capacity, site plan, crowd management, stewarding and SIA-licensed security, traffic management and parking, medical and first aid cover, fire safety and evacuation, noise management, waste and welfare, communications, and the procedure for a major incident or a show stop.
The annexes are where an application stands or falls. Expect to attach a site plan drawn to scale, your general and fire risk assessments, a traffic management plan for anything touching the highway, supplier documents including insurance and structural calculations, and evidence of public liability cover. Councils commonly set that cover at £5 million and raise it for higher-risk activity. Treat the plan as a live document: SAGs work through successive drafts and usually want the final version at least a week before the event.
The site plan is the annex that comes back most often. A reviewer has to be able to measure on it: is the fire lane still 4.5 metres wide once the food traders are in, is the emergency exit route clear, does the crowd figure you quoted actually fit the square metres you have drawn. A sketch without a scale cannot answer any of those questions, so it gets returned, and on a fixed event date that lost fortnight is the expensive part.
One practical point: supply the plan as a PDF at a fixed paper size with the scale printed on it, not as a screenshot pasted into a document. Councils working with an assessment module can then measure and mark up directly on the drawing, which shortens the review considerably.
06 THE DRAWINGS
Site plan, traffic plan and signage
Three drawings sit behind almost every event application and they answer three different questions. The festival map of your site shows how the ground is laid out, including stages, bars, fencing, walking routes and emergency exits. The event roadmap and traffic plan shows how visitors, deliveries and emergency vehicles reach the site while the road is closed. The event signage plan shows which sign goes on which post for the last few miles.
Drawing all three on the same basemap saves real time. The closure point on your traffic plan then lines up exactly with the gate on your site plan, and a reviewer can see at a glance that the two documents describe the same event.
Drawing the event site map with us is free and stays free, with no licence required. If your council already works with Traffic Chart, the basic traffic plan is free for residents and organisers in that area too.
The event map module is 100% free, forever. No trial countdown, no card on file.
Frequently asked questions about organising an event
How far in advance should I start organising an event?
Do I need a temporary event notice for my event?
What is the difference between a temporary event notice and a premises licence?
What should an event management plan include?
How do I close a road for an event?
Can the Safety Advisory Group stop my event?
Read more
Festival map maker: 100% free event-plan software →
Draw a scaled festival map in minutes: stages, bars, toilets, walking routes, fencing, emergency exits. 100% free, no card, council-ready PDF.
Event roadmap drawn in 20 minutes, 100% free →
Draw your mandatory event roadmap in minutes. 600+ traffic elements, drag-and-drop signage, automatic detours. 100% free to start, no card.
Event signage planned in minutes, 100% free →
Plan your event signage in minutes. 600+ traffic + signage elements, drag-and-drop directional signs, council-ready PDF. 100% free to start.